Lab Build: Concrete And Sockets - 17/04/17

Firstly, the concrete floor is down and dry allowing us to get a proper look at the height of everything. Unfortunately I couldn't get any photos of the concrete tube and truck as I was not present when it was done.





Secondly, the electricians have been round twice and fitted a mount at every location I wanted sockets at. They've ran cables to each one through holes in the roof and also wired the areas where the internal, external and security light will be placed. Once the plaster boards are up in a few days time's, the ugly cable holders will be covered up and all that will remain is the ends of the cables ready to be fitted to the sub panel,light fixtures and switches.










Finally, the outside has been given a proper clean up. All of the lose bricks and wood used for the scaffolding have been removed, the trench around the perimeter of the structure has been filled in with spare soil and all of the brickwork has been given a thorough clean to remove stray bits of motor and mud.



 

No comments:

Post a Comment